Week of June 22 – June 28

Posted: 06/29/2009

The garage footings and ICF’s were put in place early in the week on Tuesday the 23rd. There was a some confusion with the garage that all got worked out with an end result of us losing 3 inches of width off the garage, at one point it was going to be 8 inches so 3 is better.

Framing for the first floor started on Thursday June 25th on the same day concrete for the ICF’s was poured and dirt was being filled back in over the footings on the garage. Seeing the framing started for the first floor made us realize our house is going to be tall. Saturday the concrete slab for the garage was poured and on Sunday they came and cut it. All the pictures are up in the see our passive house section.

Categories: construction | Comments: No Comments »

This entry was posted on Monday, June 29th, 2009 at 10:21 am and is filed under construction. You can follow any responses to this entry through the RSS 2.0 feed. You can leave a response, or trackback from your own site.

Leave a Reply

XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>